Executive summary: Surging data center growth is reshaping utility planning across transmission and distribution networks. To keep pace, utilities must balance capacity expansion with flexibility—leveraging digital tools, operational technology, and new interconnection models. Adapting quickly will determine who can meet rising demand while maintaining grid reliability and protecting ratepayers.
7-minute read
U.S. data centers used roughly 176 terawatt-hours of electricity in 2023, up from 58 TWh in 2014. The U.S. Department of Energy projects data center usage could climb to 580 TWh by 2028. Fueled by the rise of AI and cloud computing, this growth is reshaping how utilities plan, operate, and invest in power infrastructure.
Instead of steady, predictable increases in demand, utilities are now managing concentrated, high-capacity loads that can exceed traditional planning cycles. Many are under pressure to deliver power at the pace required for new data centers while maintaining grid reliability and resilience.
Meanwhile, utilities are advancing sustainability and decarbonization goals, adding new layers of complexity to already stretched systems. Achieving both will require modernized operations built on data, collaboration, and digital tools that improve grid visibility and responsiveness.
Table of contents (click to expand)
- The interconnection challenge
- Load flexibility: A new opportunity in planning
- Operational technology as the backbone of modern utility operationsPMO
- Using data to forecast and manage load growth
- Strategic planning to align with data center growth
- Securing the grid in an increasingly data center–connected environment
- The future grid demands adaptability
The interconnection challenge
Across the United States, utilities are handling record volumes of interconnection requests from data center developers, many exceeding available capacity. In some regions, proposed data centers would require more power than the utility’s existing customer base consumes in total.
Before exploring solutions, it helps to understand the scale and complexity of what utilities are being asked to connect. Data centers vary widely in size, redundancy requirements, and grid connection type, as shown below.
| Type | Approx. size | Typical grid connection | Common redundancy/ availability | Representative use cases |
| Edge/ enterprise | Up to ~5 MW | Distribution (13.2–34.5 kV typical)* | N or N+1 | Corporate IT, regional operations, local content caching |
| Colocation/ regional | ~5-20 MW | Distribution or sub-transmission (34.5–69 kV typical)* | N+1 or 2N | Multi-tenant hosting, regional cloud services, content delivery |
| Hyperscale/ AI-driven | ~20 MW and up | Often transmission (69 kV and above)* | 2N or 2N+1 | Cloud platforms, AI training clusters, large-scale analytics |
*Typical voltage levels in the United States are 13.8 kV, 34.5 kV, and 69+ kV.
N: Basic capacity to support the load
N+1: One additional unit for backup (e.g., one extra generator)
2N: Full duplication of all critical components
2N+1: Full duplication plus an extra unit for added fault tolerance
Note: Approximate values for planning purposes. Actual designs and interconnection types vary by region and utility policy. Data center size ranges are indicative and vary by utility service area, site design, and technology mix. These categories are presented for planning context only, to illustrate how grid connection and redundancy need to scale with facility size.
Smaller enterprise or colocation sites—typically under 20 megawatts—connect at the distribution level through pad-mounted transformers and local substations. By contrast, hyperscale and AI-driven facilities above 20 megawatts interconnect directly at the transmission level, often requiring dedicated substations and 2N or higher redundancy to maintain uptime.
These design and redundancy expectations place extraordinary strain on transmission and distribution (T&D) planning, as each connection must meet both reliability and resiliency standards while accommodating unprecedented load growth.
Legacy approval and engineering workflows can’t keep up with the build schedules of hyperscale data centers. The growing volume and complexity of requests have exposed the limits of manual reviews and static grid models originally designed for smaller, incremental projects. Beyond sheer volume, the nature of data center loads adds further complexity. Because these facilities rely heavily on power-electronic equipment, their demand can ramp rapidly, fluctuate with compute cycles, and create harmonics that challenge traditional grid models.
Utilities are adopting digital tools such as dynamic modeling and digital twins to simulate grid behavior, test scenarios, and locate viable connection points far faster than legacy methods allow.
Utilities are also contending with challenges around data interoperability, shifting regulatory requirements, and persistent supply chain constraints. These factors can delay projects and raise costs when multiple agencies and developers are involved. Streamlining data exchange and aligning technical standards among stakeholders will be critical to keeping interconnection projects on pace.
Article continues below.
We will never sell your data. View our privacy policy here.
Load flexibility: A new opportunity in planning
Not all data center loads are created equal. While hyperscale and AI-driven sites often demand full capacity from day one, others can scale gradually or adjust consumption dynamically. Emerging “flexible interconnection” models allow utilities to connect new data centers more quickly by accounting for flexibility in how and when they draw power.
Factors influencing flexibility include
- Load ramp-up profiles
- Ability to shift or shed demand
- On-site generation and storage
- Redundancy strategies (e.g., N+1 configurations that support partial operation during constraints)
Utilities that model and plan for this flexibility can unlock capacity faster, reduce upgrade needs, and align interconnection timing with real-world load behavior.
Accelerating energization: How utilities can streamline service and expand capacity
How utility providers can streamline energization timelines through smarter planning, improved coordination, and audit-ready cost recovery
Operational technology as the backbone of modern utility operations
Rising data center demand is making operational technology (OT) the backbone of utility operations for managing interconnections and maintaining grid performance. Systems such as supervisory control and data acquisition (SCADA), advanced distribution management systems (ADMS), and distributed energy resource management systems (DERMS) provide continuous visibility and control across distribution networks. These capabilities help operators monitor grid conditions, anticipate stress points, and adjust as new high-load facilities come online.
Automation now plays a central role. Functions such as automated switching, fault isolation, and load balancing help sustain reliability even when data center demand fluctuates or expands unexpectedly. Automation also helps utilities detect and correct imbalances early, reducing outage risk and keeping power quality consistent for all customers.
Integrating distributed energy resources (DERs)—including on-site generation—provides added flexibility, especially in areas where multiple data centers compete for limited transmission capacity. When paired with responsive OT systems, these assets can ease congestion and strengthen grid resilience during periods of peak demand.
Upgrading legacy OT systems remains a critical step. Modern, interoperable architectures that support real-time data exchange give operators a live view of grid performance and the flexibility to adjust as conditions and power requirements evolve across large-scale digital infrastructure.
Article continues below.
Using data to forecast and manage load growth
Rapid data center expansion is reshaping how utilities forecast demand and plan capacity. Traditional models based on historical load patterns and gradual growth no longer reflect conditions in regions where a single facility can add hundreds of megawatts of demand within months. To stay ahead, utilities are using AI-driven forecasting tools to predict how new data centers will affect grid performance and long-term resource planning.
IoT telemetry from substations, transformers, and field assets provides early insight into stress points near large data center clusters. These continuous data streams help operators spot localized constraints, prioritize upgrades, and adjust dispatch strategies before reliability issues develop.
However, utilities still face challenges in obtaining timely and accurate information from data center customers. Many operators are unable or unwilling to share load and performance data, even under confidentiality agreements, limiting system planners’ ability to model real-world behavior and forecast growth accurately.
Bringing grid and facility data together through integrated analytics platforms strengthens both planning and day-to-day operations. When data moves freely between departments and systems, utilities can model different growth scenarios and prepare for multiple outcomes. This capability is increasingly important for forecasting the high-intensity, variable energy demands of AI workloads, which require models that evolve alongside new technologies and usage patterns.
Digital transformation in energy and utilities: Powering the future of energy and innovation
Digital transformation in utilities is revolutionizing the energy sector by enhancing efficiency, sustainability, and customer satisfaction through cutting-edge technologies and data-driven solutions.
Strategic planning to align with data center growth
Expanding data center clusters are prompting utilities to rethink how they plan and coordinate large-scale investments. Concentrated clusters of high-load customers are challenging traditional forecasting and capital planning cycles. Utilities are partnering with developers, regulators, and local governments to coordinate infrastructure upgrades around data center siting and construction schedules—and to determine who pays for them with a fair mechanism.
Flexible resource planning that incorporates microgrids, DERs, and on-site generation helps reduce strain in areas with heavy data center activity. These strategies enable utilities to balance local reliability with broader grid stability while advancing renewable integration and decarbonization goals.
Addressing supply chain constraints and interoperability gaps remains essential for maintaining project schedules and cost predictability. Collaborative planning, modular design, and scalable technologies help utilities prepare for continued data center growth while maintaining the reliability and resilience that digital infrastructure depends on.
Unlocking grid potential with flexible interconnection via DERMS
How a major West Coast utility leveraged flexible interconnection through DERMS to accelerate data center connections, optimize grid performance, and unlock new capacity without costly infrastructure upgrades
Securing the grid in an increasingly data center–connected environment
Cybersecurity is now a shared responsibility between utilities and their largest data center customers as networks become increasingly interconnected. High-capacity connections expand the number of devices on the network and create new entry points that must be monitored and secured. The stakes are high: a single breach could disrupt both digital infrastructure and the electric grid that supports it.
Utilities are reinforcing defenses with layered controls such as segmentation, authentication, and intrusion detection to isolate threats before they spread.
Ongoing monitoring, role-based access, and anomaly detection extend visibility across operational and connected device environments. Embedding cybersecurity in every stage of modernization—from design through maintenance—helps prevent disruptions and strengthen resilience across an increasingly data center–connected grid.
The future grid demands adaptability
Rising data center demand highlights a new reality for utilities: flexibility and capacity are equally vital in shaping tomorrow’s grid. Integrating operations, data analytics, and cybersecurity will help utilities manage the next wave of large-scale digital infrastructure. Developing adaptive systems will keep them ahead of the curve as AI-driven data centers expand and evolve.
As utilities modernize the grid to support this surge, both regulatory and technical flexibility will be critical. Emerging flexible interconnection models—based on more dynamic load forecasting and shared operational data—can accelerate project timelines while reducing system strain.
At the same time, cost allocation and ratepayer protection will remain central considerations. Determining who bears the expense of infrastructure upgrades—developers, utilities, or ratepayers—will require transparent collaboration among regulators, policymakers, and industry leaders to balance grid resilience with equitable investment.
Making that shift takes more than new tools. It calls for a mindset grounded in collaboration, agility, and decisive action. The next phase of grid modernization will depend less on scale and more on utilities’ ability to anticipate change and navigate complexity across a rapidly transforming energy landscape.
References
https://www.camus.energy/blog/how-flexible-interconnections-can-help-data-centers-connect-faster-without-overloading-the-grid
https://www.powermag.com/blog/data-centers-can-be-a-flexible-power-load-heres-why-that-matters/
https://eta-publications.lbl.gov/sites/default/files/2025-03/final_doe_data_center_load_flexibility_workshop_summary.v0307.pdf
https://mitsloan.mit.edu/ideas-made-to-matter/flexible-data-centers-can-reduce-costs-if-not-emissions
https://www.gevernova.com/consulting/resources/articles/2025/data-center-interconnection-planning
You might also be interested in …
Microgrids: Transforming energy resilience and efficiency
How microgrids are enhancing energy resilience and transforming grid operations through innovative, real-world applications
How intelligent automation is shaping a more reliable power grid
Faced with pressures to enhance reliability, utilities are leveraging intelligent automation and reaping the rewards.
The IT/OT PMO: Governance as the catalyst for utility modernization
A unified IT/OT PMO provides the structure needed to manage risk, meet regulatory demands, and deliver lasting operational value.
Powering a sustainable tomorrow
We partner with utilities to help them build a more resilient grid and move towards a cleaner, brighter future through
- AI-driven automation
- Asset image analytics
- DERMS implementation
- Analytics & predictive insights
- Cloud optimization